September 15, 2007

A Busy Weekend Ahead

fbhasmoved.jpg
There's a busy weekend ahead for the LCFs. N747BA (LCF1) was spotted at PAE on Friday loading shipping fixtures for this weekend's trip to Japan and N780BA (LCF2) is in Charleston prepping for it's trip to Italy. Both LCFs are expected to leave their respective bases Saturday or Sunday and are scheduled to return around 1pm on Monday, September 17 in Charleston.

LCF2 will deliver Sections 44 and 46 from Grottaglie. Look for the outbound leg to operate as EIA5162 and return as EIA5127.

LCF1 will deliver Sections 45, 11 and 43 from Nagoya. The outbound leg to Japan should operate at EIA5109 and return as EIA5186.

When assembled together, these sections will make up the center fuselage of Dreamliner Three. Currently fuselage parts are scattered across the US. Section 41 is under construction in Wichita and Section 47 and 48 are being assembled in Charleston.

In addition, the center fuselage for Dreamliner Two is making great progress in Charleston. Work continues installing the key ceiling brackets that will hold the wiring, environmental control systems and ducting. Delivery to Everett is set for those first two weeks in October. Keep an eye out for Dreamliner Two to possibly be the first to fly, followed very closely by Dreamliner One. I am working to confirm this.

I too will be busy this weekend and don't anticipate being able to update in a significant way for several days. Feel free use the comments section here as an open thread for discussion. Not to worry, I haven't forgotten, the 747-8 update will be arriving shortly.

September 11, 2007

Tweaking The Schedule, Part Two

fbhasmoved.jpg
All is quiet tonight in Everett.

Dreamliner One is still off of its landing gear. ZY997 can't move to Building 40-23. The delay in first flight has reduced the urgency of the move. However, if the urgency was the same the aircraft would be unable to move. The spotting opportunity to see ZA001 and ZY997 together should come soon however.

As a result of the bottleneck preventing an assembly space from opening in Building 40-26, the delivery of ZY998, the Fatigue Airframe, has been postponed an additional 10 days. Shipment to Washington was originally planned for September 20. The delivery to Everett is now expected around September 30.

The pair of LCFs will be working this weekend. All major structures for the center fuselage of LN3/ZA003 will arrive from Japan and Italy on Sunday, September 16. They are scheduled to arrive at CHS within 45 minutes of one another. Parts forLN4/ZA004 should be arriving in Charleston two weeks after.

August 27, 2007

August 27, 2007

fbhasmoved.jpg
I am back after a short (and much needed) vacation. I've tweaked the design for these updates to make information more accessible. A master list of all updates will still be available at its original page: The Dreamliner Learns to Fly.

Everett:
Structural, wiring and systems installation continues on Dreamliner One as it has since July 9th. At last word, the flight deck only had rudder pedals installed. The vertical tail has not yet been reattached, however the aft pressure drogue has installed in preparation for flight test. An ANA painted rudder has arrived in the rear of the factory in Building 40-36. This is destined for Dreamliner Two when final assembly begins in October. The aircraft is likely to wear full ANA paint. Passenger doors 1 and 2 have been installed on the Static Rig which is still in the number one position inside Building 40-26.

UPDATE: The vertical tail (without the rudder) was reattached to the fuselage on Sunday, August 26.

Charleston:
With the change in delivery order, work in Charleston has shifted to the Fatigue Airframe (ZY998). Section 45/11 and 44 have been joined and Sections 46 & 43 are being deburred and drilled in preparation for completion of the center fuselage. Limited work continues on Dreamliner Two with the installation of clips and fittings.

August 22, 2007

Tweaking The Schedule

The relocation of the Static Air Frame to Building 40-23, which was tentatively scheduled for the night of August 23rd, has been pushed back to the night of September 11th. This will undoubtedly be an extraordinary opportunity for spotters to see two 787s at once.

In addition, Flightblogger has learned that Dreamliner Two final assembly is now scheduled to begin October 9th. Assembly was initially set to begin after the arrival of major structural parts to Everett on August 18th, however Boeing has reworked its delivery schedule with its sub-assembly partners.

August 20, 2007

Boeing faces hurdles, opportunities on the road to an on-time 787 entry into service

fbhasmoved.jpg
According to multiple sources inside the 787 program, Boeing has delayed delivery of major structural parts for Dreamliner Two indefinitely as work feverishly continues on preparing Dreamliner One for its first flight this fall.

Put simply, there is a small bottleneck inside of Building 40-26 at the Boeing factory in Everett interfering with deliveries. Two of the four final assembly positions are in use. The first position in the rear of the factory is occupied by the Static Rig (ZY997), the second by Dreamliner One (ZA001).

Dreamliner One continues to undergo extremely extensive structural and systems assembly and is currently jacked up off its landing gear surrounded by scaffolding, making the forward movement to make way for the Static Rig difficult until it returns to pavement.

Dreamliner One undergoing extensive assembly in Everett

In addition, Flightblogger has learned that once deliveries do resume, the Fatigue Test Rig (ZY998) will be delivered prior to Dreamliner Two (ZA002).

Mary Hanson, spokeswoman for the 787 program confirmed that a change in the delivery schedule existed, “The 787 program has directed several structural partners to re-look at their ship dates on [Dreamliner Two] and complete systems, wiring and other critical installations before shipping to final assembly.”

Hanson added that the delay has nothing to do with Dreamliner One, and felt the characterization of the schedule change as a postponement or delay was not accurate, and that first flight, certification and entry into service are not affected by this decision. Hanson also declined to comment on the bottleneck inside Building 40-26.

According to sources, Boeing’s public stance on the delay is accurate with regard to the travel work; however the delay in deliveries is in part due to the around-the-clock singular focus of the final assembly team on preparing Dreamliner One for its maiden flight.

With Dreamliner One in its current position, there is no room in the rear of the factory to begin final assembly of the Fatigue Test Rig or Dreamliner Two. Delivery of Dreamliner Two structures from South Carolina, Kansas, Japan and Italy were all initially planned for an August 18 timeframe.

In addition, Dreamliner One still has yet to have its tail, engines, wing-body fairing, flaps and landing gear doors reinstalled following a comprehensive disassembly which occurred after the July 8th roll-out ceremony.

"Boeing is doing everything they can to finish the job but there are jobs that just cannot be sped up," said one Boeing employee with knowledge of the program.

Testing on the Static Rig needs to take place three doors down in Building 40-23, which is located between the 747 and 767 final assembly lines. Before the Static Rig can move to Building 40-23, Dreamliner One must be rolled out of the factory. The width of Building 40-26 is only large enough to accommodate one 787 at a time.

According to sources who have seen Boeing's internal schedules the Static Rig is tentatively scheduled to move out of 40-26 on August 23. The move will take place during the late night shift change just as it did for the appearance of Dreamliner One when it left the factory for the paint shop on June 25.

The indefinite delay of continued deliveries to Everett present a distinct problem for Boeing, which has an ambitious nine month flight test program planned. The test program will employ four aircraft (ZA001-ZA004) as the 787 Dreamliner seeks certification with Rolls Royce Trent 1000 engines for entry into service in May of 2008 with All Nippon Airways.

Without a second, third and fourth 787 to quickly join Dreamliner One on the rigorous flight test regime, Boeing will be hard-pressed to meet its May 2008 EIS goal. As an important point of comparison, the first and second 777 aircraft flew 32 days apart in 1994 and the third 777 followed just 22 days later. The 777, the last all-new Boeing aircraft, completed an eleven-month, five aircraft flight test certification program in April 1995. The 787 certification program will likely have to match or exceed the pace of aircraft introduction on the 777 program to meet its goals.

Facilities in Charleston and Wichita are working around-the-clock to prepare 787 fuselage sections for final assembly and delivery to Everett. The first 787 fuselage pieces delivered to Everett were almost entirely bare of systems and represented mainly the structural shell of the aircraft. Extensive "travel work" is being currently performed by the final assembly team in Everett to install wiring, ducting, insulation and systems for the first 787.

The indefinite delay in deliveries to Everett could also provide an opportunity for Boeing to test its groundbreaking business model. Boeing hopes that by delaying deliveries to Everett, they can allow the 787 subcontractors to more fully complete the assembly of follow-on aircraft fuselage sections.

Section 46 for ZY998 arrives in Charleston

The deferment of assemblies will allow for independent work to be done outside of Puget Sound, enabling the Everett-based final assembly and delivery team to continue its focus on Dreamliner One. Once Dreamliner One has been fully assembled, the follow-on fuselage structures can be joined in less time in hopes of keeping the flight test, certification and delivery on track.

Hanson added, “To allow traveled work to continue to flow from our partners into final assembly would deter the 787 program from setting up the Lean production system we envision. [The change] is necessary and will enable the program to get the right production system up and running over the long term.”

Another source, a veteran engineer of Boeing commercial aircraft programs, including the 787, is concerned about the planning moving forward.

“Boeing needs to look at the certification date and work backwards from those milestones looking at how to achieve this program goal by goal. Right now they are moving forward, but there’s no connection between milestones.”

Deliveries to sub-contractors are expected to continue with fuselage sections arriving in Charleston from Italy and Japan; however no timeline for the next deliveries appear to be in place.

The veteran engineer added, “There’s a lot of energy and time being wasted. Teams all over the globe are ready to work. The [Large Cargo Freighter] should be moving empty fixtures back to their respective partners' manufacturing locations. This could be done while Evergreen International flight crews are doing required training. Forward motion is essential - even if it’s slow progress, it’s still progress.”

August 15, 2007

Flightblogger Exclusive: Window Seats

fbhasmoved.jpg
There has been an ongoing debate inside the aviation enthusiast community since the beginning of the 787 program. The question has been repeated more times than I can count:

Are the 787 windows really any bigger?

I would like once and for all to put this debate to rest.

They ARE bigger. In fact, they are HUGE.

18.4 inches tall by 10.7 inches wide.
We've heard the numbers and we've seen the pictures. What follows are the actual window frames developed by Alenia that are slated to be installed on Dreamliner Two. One day in the not so distant future, a passenger will look out this window on a flight on an All Nippon Airways 787. To illustrate the actual size of these windows there is a tape measure in the picture that shows the size of the window in both metric and English units. They are at full resolution so you can read them clearly. Please feel free to click the images to view the larger versions.



The final image is the Dreamliner Two Center Fuselage (which will receive these window frames) in all her glory being assembled by the Charleston "Dream Team" which has identified, tackled and solved the challenges placed in front of them with extraordinary skill and grace. The work they are doing is truly incredible. Since this photo was taken, there has been significant work done on the center fuselage section including the installation of ducting, insulation and other key systems.

All images are exclusive to Flightblogger not to be reposted or published without prior consent.

July 17, 2007

Changing Flight Numbers

Flightblogger has learned that the modified 747 LCF2 has changed its call sign from Boeing 632 to Evergreen 5146 and Evergreen 5104. 5146 represents the leg from Wichita to Charleston and 5104 represents Everett to Wichita. Flightblogger is working to confirm the permanent change in LCF flight numbers. Either way, it looks like Section 41 for ZA002 should be coming to Everett very soon.

UPDATE: LCF2 will return to Everett tonight as Evergreen 5169 with an estimated arrival at 6:12PM PDT.

June 28, 2007

A Busy 747

While all eyes were on Dreamliner One heading to the paint shop yesterday, LCF2 was busy working overtime.

N780BA, Large Cargo Freighter 2, returned to Charleston Tuesday from Italy (after a fuel stop in Scotland) with Section 44 and 46 in tow for the second flying test frame ZA002. After arriving in Charleston just before 5pm EDT on June 26, LCF2 turned around two hours later and departed on its way to Everett.

LCF2 arrived in Everett around 9:30 PDT June 26. The full scale static test rig will be assembled and put through its paces in Building 40-23, two bays down from the location of the 787 assembly line.

The modified 747 turned around and departed from Everett (this morning) at around 4am on June 27 for Japan. LCF2 should return to the Pacific Northwest by Thursday.

Boeing 632 Flight Plan
Everett (KPAE) to Nagoya (RJGG)

TOU TR13 SPONJ ORNAI 5200N 14000W 5400N 15000W 5500N 16000W CDB A342 OLCOT R580 OATIS OTR3 GOC W18 SWING

Update: LCF2 returned to Everett without the center fuselage for ZY9997 as previously reported. The center fuselage for the static test rig continues to be assembled in Charleston. On its way back from Japan, the 747 stopped in Everett for fuel and continued on to Charleston with Section 43 and 11/45 for ZA002 aboard, not the wings as previously thought.